Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

January 2014

  • The general excavation (6th level) along with the temporary retaining structures in the area of KORYDALLOS Station are at a completion percentage of 89%;
  • The worksite fencing in TAXIARCHON Shaft in AGHIA VARVARA Station is in progress;
  • The main excavation works in the area of NIKEA Station (C/C) is at percentage of 66%, while the construction of pre-stressed anchors is at percentage of 72%;
  • The construction of piles in the area of MANIATIKA Station is in progress.
Print Friendly, PDF & Email
WCAG