Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
  • NEW RAILWAY Station: The works for the backfilling of the roof slab were completed, while the works for the construction of the NW & NE shaft at the crossover, and the works related to the preparation of the modification of the traffic phase are at an advanced stage;
  • DIMOKRATIAS Station: The works for the removal of the metal propping of the northern roof slab has commenced;
  • AGHIA SOFIA Station: Following the final opinion of the Central Archaeological Council, the removal of the archaeological finds in the framework of the archaeological excavation (Phase A’) at the southern part of the Station was completed;
  • SINTRIVANI Station: The excavation works at the 4th level (platform) and the archaeological excavation works at the southern ventilation shaft have commenced, while the works for the construction of walls at the 3rd level are in progress;
  • PAPAFI Station: The preparatory works for the installation of the last row of struts and the works for the preparation for the traffic phase modification have commenced, while the works for the construction of the western access are at an advanced stage;
  • EFKLIDIS Station: The works for the construction of the platform and the works for the installation of the escalators are at an advanced stage;
  • ANALIPSI Station & Crossover: Excavation works at the 3rd level (platform) have been completed;
  • PATRIKIOU Station & Crossover: The works for the construction of the sewage pipe shaft, as well as the dismantling of the old pipe, have been completed;
  • NEA ELVETIA Station & Crossover: The excavation and retaining works are at an advanced stage;
  • DEPOT: The works for the construction of parapet walls and columns of building No. 9 have commenced, while the archaeological excavation at a part of the Depot is in progress;
  • Tunnels: The works for the construction of piles – cap beams, as well as the works for the diversion of PUOs at the C/C tunnel are in progress.
Print Friendly, PDF & Email
WCAG