Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
  • DIMOCRATIAS Station: The construction of conventional parapet walls southwards is in progress;
  • SINTRIVANI Station: The excavation works at level 2 were completed, while the construction of slab at level 3, the construction of NATM ventilation tunnel and the archaeological excavation works at the northern access are in progress;
  • PANEPISTIMIO Station: Civil works were completed up to level 3;
  • PAPAFI Station: Excavation works at level 2, the works for the diversion of PUO networks at the southern entrance, as well as the construction of piles at the southern access are in progress;
  • ANALIPSI Station & Intersection: The construction of the slab at level 2 was completed. Excavation works at level 3 have commenced, while the construction of piles at ventilation shafts 2 & 3 and the installation of struts for the construction of the eastern access are in progress;
  • NEA ELVETIA Station & Intersection: The construction of shaft piles was completed, while excavation and temporary retaining works are in progress (anchors, struts, shotcrete);
  • DEPOT: The works for the construction of the foundation slab of building I were completed, while the works for the construction of parapet walls and columns of building I, the construction of cap beams & piles, as well as the excavation works in the area of building II (OCC) are in progress;
  • The works for the relocation of the two TBMs at Nea Elvetia Intersection are in progress.
Print Friendly, PDF & Email
WCAG