February 2013

  • The civil works at the forestation of the New Railway Station and at SYNTRIVANI Crossover have been completed;
  • The archeological excavations at VENIZELOU Station are in progress;
  • The construction of the 3rd level at PANEPISTIMIO Station has been completed, while the works for the construction of the 1st level of AGHIA SOFIA Station have been completed;
  • The works for the construction of the Diaphragm Walls at ANALIPSI Station are in progress.