Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

March 2016

  • NOMARCHIA Station: The works for the installation of metal struts at level -2 are in progress.
  • NOMARCHIA Crossover: The works for the installation of metal struts at level -1 were completed. The excavation works of level -2 and the works for the installation of metal struts at level -2 are in progress.
  • ARETSOU Station: The works for the excavation of the station are in progress.
  • NEA KRINI Station: The works for the construction of the roof slab and the walls at level -1 are in progress.
  • MIKRA 1st Crossover: The construction of temporary retaining piles is in progress.
  • MIKRA 2nd Crossover: The works for the construction of perimeter piles’ cap beam were completed. The works for the installation of metal struts and for the construction of anchors at the 1st level are in progress.
  • The preparation and approval of designs are in progress.
Print Friendly, PDF & Email
WCAG