November 2015

  • NOMARCHIA Station: Works for the perimeter piles and piles cap beam have been completed, while the construction of struts made of reinforced concrete at level -1 are in progress.
  • NOMARCHIA Crossover: Works for the construction of perimeter retaining piles and their cap beam have been completed. The works for the construction of struts made of reinforced concrete, as well as for the diversion of PUO networks are in progress.
  • KALAMARIA Station: Works for the construction of perimeter piles at the eastern section of the station have been completed. Works for the construction of perimeter piles cap beams, struts made of reinforced concrete, as well as works for the diversion of PUO networks are in progress.
  • ARETSOU Station: Works for the construction of perimeter retaining piles are in progress.
  • NEA KRINI Station: Works for the construction of a pumping station on the station raft, works for the construction of perimeter walls at level -2, platforms and part of the slab at level -1 are in progress.
  • MIKRA Forestation: Works for the construction of perimeter retaining piles, for the configuration of the worksite and general excavation works are in progress.
  • Terminal Shaft: The construction of perimeter piles is in progress.
  • Kritis shaft: The excavation of the 2nd phase and the construction of a temporary retaining wall are in progress; the installation of the1st level metal struts has been completed.
  • Pontou shaft: The construction of perimeter piles and the configuration of the worksite area are in progress. Moreover, excavation works are in progress for the construction of perimeter piles cap beam.
  • The preparation and approval of designs are in progress.
  • The expropriation of areas in ARETSOU, MIKRA (part) Stations and MIKRA Forestation has been completed, while the supplementary expropriation of an area in a small part of MIKRA Station is still pending.