August 2015

  • NOMARCHIA Station: The works for the construction of retaining piles at the perimeter of the station were completed. The works for the construction of a pile cap beam are in progress;
  • KALAMARIA Station: Works for the construction of piles at the western part of the station are in progress;
  • NEA KRINI Station: Works for the excavation of the station were completed. The works for waterproofing the station invert are in progress;
  • MIKRA Station: The excavation of the 2nd NATM tunnel is completed. The excavation of the 1st NATM tunnel is in progress;
  • Preparation and approval of designs is in progress;
  • 2nd crossover MIKRA: Investigation trenches and piles’ construction related works are in progress;
  • The preparation and approval of designs are in progress;
  • The expropriation of areas at ARETSOU Station, at a section of MIKRA Station and at MIKRA Forestation is still pending.