April 2015

  • NOMARCHIA Station and Crossover: Piling works for the temporary retaining and the foundation of the building crane have commenced. Works for the occupation of the worksite are in progress, while works for the diversion of PUO networks are at an advanced stage;
  • KALAMARIA Station: Works for the occupation of the worksite and traffic arrangements are at an advanced stage, while works for the diversion of PUO networks are in progress;
  • NEA KRINI Station: The construction works of the Station’s retaining system (struts, cap beams, shotcrete, walls) are at an advanced stage. General excavation works are in progress;
  • MIKRA Station: The works for the excavation of the NATM tunnel have commenced. Moreover, the works for the construction of the temporary retaining system (prestressed anchors, bored piles) are at an advanced stage, while TBM start-up shaft excavation works is at a completion stage;
  • KRITI Shaft: Temporary traffic arrangement works and PUO networks diversion works are in progress. Worksite occupation works and piling works for temporary retaining have commenced;
  • Preparation and approval of designs in progress;
  • The expropriation of areas at ARETSOU Station, MIKRA Station portion and MIKRA Forestation is still pending.