September 2015

  • The works for the relocation of sewage networks at Omiridou Skylitsi street, between Ippodamias & 34th Syntagmatos streets, have been completed. In progress are the relocations of the following networks: sewage and EPA at Vassileos Georgiou concurrently with the archaeological works, EYDAP water supply networks at the sidewalk adjacent to Grigoriou Lambraki street, sewage network at Omiridou Skylitsi street & street lighting at the at the sidewalk adjacent to Grigoriou Lambraki street.
    The archaeological excavation at the trenches excavated for the relocation of PUO networks at Grigoriou Lambraki and Vassileos Georgiou streets is in progress;
  • Tramway trackwork concreting works have been completed at Myrtidiotissas Bridge. Trackwork construction works are in progress at Papandreou Bridge and at M. Asias Street. Catenary poles foundation works have been completed at Mikras Asias Street and at Lambraki Street reversing, while in progress are the investigation trenches for poles foundation at the remaining locations of the project (Gr. Lambraki, Georgiou, Eth. Antistaseos, etc. Streets)
  • The urban planning at the sidewalk opposite Ethnikis Antistaseos Street, Mikras Asias (junction with Sarantaporou Street), Gr. Lambraki (between Bouboulinas and Georgiou Street) has been completed, while the installation of underground waste bins and the relevant urban planning at Agriniou Street has been completed. Urban planning works have commenced and are in progress at the sidewalk adjacent to Mikras Asias sidewalk, at the sidewalk adjacent to Ethnikis Antisasseos sidewalk, the re-development of Akti Themistokleous and Zanni junction, while the installation of underground waste bins and the relevant urban planning at 34th Syntagmatos Street are in progress.