August 2014

  • Investigation trenches have been drilled at the locations where twin underground litter bins at Gr. Lambraki Street are to be placed;
  • The works for the construction of Myrtidiotissas bridge have commenced, while the technical works in several locations of the TRAMWAY route are in progress (in the area where KARAISKAKI stop is foreseen to be located, in Lambraki reverse, maintenance works at Lambraki bridge, etc.);
  • The works for the relocation of the sewage and water-supply pipe in Micras Asias Street have commenced;
  • The works for the relocation of the sewage pipe at Gr. Lambraki Street and the relocation of PPC networks at Lambraki reverse have commenced.