Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
  • NEOS SIDIRODROMIKOS STATHMOS Station: In progress is the archaeological excavation at the southeast and southern shaft, as well as the installation of escalators.
  • Dimokratias Crossover: Works for the construction of the northern part foundation micro-piles have been completed, while there are still in progress at the southern part.
  • DIMOKRATIAS Station: In progress are works for the construction of foundation micro-piles, the installation of struts at the northern shaft, the construction of anchors at the southwest ventilation shaft and the northern access. In addition, in progress is the archaeological excavation at the southern access and at the southwest shaft, while it has been completed at the northwest shaft.
  • SINTRIVANI Station – REPORT: The construction of the invert slab and the traffic diversion have been completed. In progress is the construction of the platform, while the construction of the piles at the southern access has commenced.
  • PANEPISTIMIO Station: The construction of the platform has been completed, while in progress is the construction of masonry walls and the installation of escalators.
  • PAPAFI Station: The construction of the slab of level -2 has been completed, while in progress is the construction of walls at level -2 to level -1, the construction of the slab of level -1, as well as the works at the northern ventilation shaft.
  • ANALIPSI Station and Crossover: The construction of the roof slab of the northern shaft has been completed. In progress are preparation works for the arrival of the two TBMs at the crossover, as well as the works for the construction of the slab at level -1 of the northern shaft and of the eastern access.
  • PATRIKIOU Station and Crossover: The construction of the underground jet grouting strut has been completed.
  • VOULGARI Station: The construction of the permanent Station box has been completed. In progress is the construction of the roof slab and the temporary retaining piles at the accesses.
  • DEPOT: Building complex II – in progress is the construction of pile cap beams in the washing plant area.
  • Cut and Cover Tunnel – Section II: In progress are works for the construction of cap beams, excavation and temporary retaining works. Section III: Excavation and temporary retaining works are in progress.
Print Friendly, PDF & Email
WCAG