January 2017

• NOMARCHIA Station: The construction of the slab at level -2 has been completed, while in progress is the construction of the permanent lining from level -2 to level -1.

• NOMARCHIA Crossover: In progress is the construction of the permanent lining from level -1 to the roof level.

• KALAMARIA Station: The construction of the pumping station walls and the waterproofing of the final level and the perimeter walls have been completed. In progress is the construction of the foundation slab.

• ARETSOU Station: The construction of the pumping station walls has been completed, while in progress is the construction of the permanent lining from the invert slab to level -2.

• NEA KRINI Station: In progress is the construction of the TBM trackbed.

• MIKRA Station 1st Crossover: At the completion stage is the construction of perimeter walls up to level -1.

• MIKRA Station: In progress is the construction of the invert slab and the TBM worksite installations.

• MIKRA Forestation – Sections 4-5: The waterproofing of the final level is in progress.

• Design preparation and approval in progress.