• NEW RAILWAY Station: The archaeological excavation at the south shafts is complete. The excavation and the temporary retaining of the southern shaft are in progress.

• DIMOKRATIAS Station: The construction of the temporary retaining at the southern access is in progress.

• SINTRIVANI Station – EXPO: The construction of masonry walls at level -1 is in progress.

• SINTRIVANI Crossover: The backfilling of the roof slab is in progress.

• PANEPISTIMIO Station: The reinstatement of the surface of the diaphragm walls is in progress.

• EFKLEIDIS Station: Plastering works at levels -1 and -2, doors installation and painting works at levels -1, -2 and -3 are in progress.

• FLEMING Station: The temporary retaining of the western access, the excavation and the temporary retaining of the northern and southern shaft and the construction of the masonry walls at levels -1 and -2 are in progress.

• PATRIKIOU Station and Crossing: Level -2 slab of the crossing has been completed. The excavation of level -3 of the station and the construction of the pile cap beam at the northeast shaft are in progress.

• VOULGARI Station: Excavation works at level -3 have been completed. The construction of level -3 slab and the excavation and temporary retaining of the eastern ventilation shaft are in progress.

• NEA ELVETIA Station and Crossover: The works for the construction of the platform have been completed. The construction of perimeter walls at level -1 of the station is in progress.

• Depot: At Building Complex II, the construction of the roof slab of the washing plant has been completed. The construction of tanks is in progress.

• TBM Tunnels: The dismantling of TBM 2 has been completed.

The dismantling of the networks in track 1 and the dismantling of TBM 1 are in progress.

• Cut and Cover Tunnel – Section I: The construction of the permanent lining is in progress. Section II: The excavation, retaining and construction of the permanent lining are in progress.