Kalamaria Project progress

  • Home
  • Kalamaria Project progress
Καλαμαριά - Φεβρουάριος 2022

February 2022

• NOMARCHIA Station (Station and Crossover): In the station, in progress are preliminary works for the installation of Platform Screen Doors (PSD). In the area of the crossover, in progress are works for the installation of ceramic tiles and the installation of trays. • KALAMARIA Station: In progress are works for the installation of traffic […]
Read More
Καλαμαριά Ιανουάριος 2022

January 2022

NOMARCHIA Station (Station and Crossover): In progress are works for the installation of industrial roller shutters, stainless steel balustrades and cabling installation works in the escalators. In the area of the crossover, in progress are works for the construction of sewage network, painting works and works for the installation of the fire detection network. KALAMARIA […]
Read More
Καλαμαριά Οκτώβριος 2012

October 2021

NOMARCHIA Station: In progress are works for the installation of granite tiles on parapet walls and skirting at the central staircase. KALAMARIA Station: In progress are works for the reinstatement of the central island at Pontou street, the installation of glass panes at the east and west entrances, as well as works for the installation […]
Read More
Καλαμαριά Νοέμβριος 2021

November 2021

• Kritis Shaft: Preliminary works for the industrial flooring and waterproofing of the station are in progress. • NOMARCHIA Station (Station and Crossover): Reinstatement works at the station street-level are in progress, as well as works for the installation of stainless steel balustrades in the areas where passengers will move. At the crossover preliminary reinstatement […]
Read More
Καλαμαριά Δεκέμβριος 2021

December 2021

NOMARCHIA Station (Station and Crossover): In the area of the crossover, in progress are painting works and works for the installation of the automatic fire fighting system. ARETSOU Shaft: In progress are works for the installation of collectors for the automatic fire fighting system. NEA KRINI Station: In progress are works for the installation of […]
Read More
Καλαμαριά Σεπτέμβριος 2021

September 2021

  The equipment of the Platform Screen Doors has been delivered in all stations. • Kritis Shaft: Preliminary works for the industrial flooring are in progress. • NOMARCHIA Station (Station and Crossover): Works for the construction of granite water discharge grooves at the central staircase are in progress. At the crossover works for the backfilling […]
Read More
Καλαμαριά Αύγουστος 2021

August 2021

KALAMARIA Station: Preliminary works for the implementation of the 10th traffic arrangement and works for the installation of lighting fixtures and tray earthing works are in progress. NEA KRINI Station: Surface reinstatement works and works for the installation of lighting fixtures and tray earthing works are in progress. MICRA Station (Station & Crossovers): Works for the installation of the fire-fighting system […]
Read More
Καλαμαριά Ιούλιος 2021

July 2021

NOMARCHIA Station (Station & Crossover): Street-level reinstatement works, works for the installation of stainless steel balustrades and handrails at the entrance staircase and works for the installation of lighting fixtures are in progress. At the crossover, concreting works of the roof slab for closing of the opening and waterproofing works are in progress. KALAMARIA Station: Preliminary works for the implementation […]
Read More
Καλαμαριά Ιούνιος 2021

June 2021

NOMARCHIA Station (Station & Cross Over): At the cross-over, concreting works at the intermediate slab for closing of the opening are in progress. ARETSOU Station: Surface reinstatement works are in progress. MICRA Station (Station & Cross Overs): In the area of the 2nd cross-sections, in progress are surface reinstatement works and works for the installation of the fire-fighting system. TRACK WORK In progress are works for the installation of the […]
Read More

May 2021

NOMARCHIA Station (Station and Crossover): In progress are cladding works using fibre-cement boards at the central staircase, as well as works for the installation of the fire fighting network and HVAC system related networks. KALAMARIA Station: In progress are traffic arrangement works, works for the installation of metal frames and glass panels at shops and the atrium, […]
Read More