- The delivery and assembly of the bentonite processing facilities is in progress, as well as the drilling of micro-piles in PATRIKIOU Station;
- The works for the construction of retaining struts at level-3 of FLEMING Station are in progress;
- The excavation works at the first level of Dimokratias Junction are in progress.