Project progress

Project progress

The most extensive transport project of Thessaloniki, a modern Metro network of high aesthetics, comes to life. More than 650 persons of various disciplines work on a daily basis for Thessaloniki Metro, while a total of 16 worksite areas have been developed throughout the city by the contracting Joint Venture.

Thessaloniki Metro, a 9.6 km network, shall have 13 modern stations, 18 fully automatic and air-conditioned trains, as well as platform screen doors in all stations, ensuring the provision of the optimum services to the passengers and their maximum safety. A 50,000 m2 depot is also foreseen in the area of Pylea.

It is worth pointing out that by incorporating state-of-the-art technical features in combination with the most stringent quality and operability standards, Thessaloniki Metro shall become the most advanced Metro network in Europe.

Print Friendly, PDF & Email

PROGRESS OF WORKS

May 2018

NEW RAILWAY Station: the configuration of the surrounding area is in progress.

• DIMOKRATIAS Station: The installation of metal doors at levels -1 and -2 of the station and the backfilling of the south access of the station are completed. The construction of the station’s walls and the implementation of traffic regulation – phase K’ at the intersection are in progress.

• VENIZELOU Station: The dismantling of diaphragm walls in the areas of the north and south access is in progress.

• SINTRIVANI Station – EXPO: Completed are the construction of the south access, the construction of terminations and parapet walls at the south access and the configuration of the surrounding area at the south access. In progress is the implementation of traffic arrangement – phase E’.

• PAPAFI Station: The following works are in progress: painting of the shafts, wall cladding with ceramic tiles, construction of gypsum boards and E/M installations (cable trays, earthing, sewage, fire fighting, fire detection, HVAC air ducts).

• EFKLIDIS Station: Floor lining with granite tiles at level -1 has been completed. In progress are the configuration of the surrounding area, the installation of balustrades at the emergency exit staircases and the wall cladding with granite slabs.

• FLEMING Station: Painting works are completed, while is progress is the installation of metal doors, the installation of outdoor grating at the ventilation shafts, as well as the E/M installations (sewage, fire fighting, fire detection, LV cables, lighting, blast shafts equipment).

• ANALIPSI Station & Crossover: In progress are works for the construction of industrial floors, wall plastering and painting works at the crossover and the Station shafts.

• 25 MARTIOU Station & Crossover: The construction of the east access has been completed, while painting works and works for the installation of metal doors are in progress.

• NEA ELVETIA Station and Crossover: The construction of the south access of the station, as well as of the PPC manhole has been completed. In progress are waterproofing works at the south access and in the PPC manhole, works for the installation of metal doors in the station, painting works at the crossover and E/M works (water supply, sewage).

• Depot – Building Complex I: The following works are in progress: construction of skylights on the roof of the metal structure, installation of window frames and the construction of gypsum board lining in sanitary areas, the offices and building No. 7. Building Complex II: The following works are in progress: construction of gypsum boards in OCC and in building No. 9, the construction of roof at section IV, the construction of side coverings at the north façade of the OCC and the installation of rails.

• Cut & Cover (C&C) and NATM Tunnels: (EYATH) pipes currently returned to their original location at sections II and III, while the reinstatement of sidewalks on Allatini street is in progress.

Print Friendly, PDF & Email

February 2018

  • NEW RAILWAY Station: Implementation of traffic phase E’, as well as plastering and masonry wall related works have been completed. The works for the construction of shaft terminations are in progress.

• AGHIA SOFIA Station – north access: The archaeological excavation in progress.

• SINTRIVANI Station – EXPO: The excavation and temporary retaining works at the south access have been completed. The the construction of the south access and E/M installations are in progress.

• PANEPISTIMIO Station: Masonry works are in progress.

• PAPAFI Station: The implementation of traffic phase E’ has been completed, while the reinstatement of the central traffic island on Karamanli Avenue is in progress.

• FLEMING Station: Masonry works and the implementation of traffic phase E’ have been completed. Door installation works are in progress.

• 25 MARTIOU Station & Crossover: Plastering works are in progress.

• VOULGARI Station: Masonry works and the installation of escalators are in progress.

• NEA ELVETIA Station and Crossover: Works for the construction of PPC manhole in the station, as well as crossover masonry works are in progress.

• Depot – Building Complex I: The construction of the metal structure roof, plastering works in the washing plant and works related to E/M installations are in progress. Building Complex II: The following works are in progress: metal roof painting works using fire resistant paint, masonry, plastering and painting works, as well as works related to E/M installations. In the surrounding area, the construction of E/M routing infrastructure and the backfilling between complexes IK and II are in progress.

• TBM Tunnels: The works for the construction of the tunnel walkways’ foundation are in progress from ANALIPSI Station to SINTRIVANI Crossover.

• Cut & Cover (C&C) and NATM Tunnels – Section I: Joint sealing works are in progress.