Extension to Kalamaria

Extension to Kalamaria

Thessaloniki Metro line is currently being extended towards the areas of Nomarchia, Kalamaria, Aretsou, Nea Krini and Micra. This underground extension shall be 4.78km long with 5 new Stations. More precisely, the project concerning the first extension of Thessaloniki Metro to Kalamaria was tendered on May 6th, 2009 and the relevant contract was concluded on June 2013 with AKTOR ATE Joint Venture. The total budget of the project amounted to 518 million (400 million € concern the contract in question). This project has been integrated in the National Strategic Framework – “Macedonia – Thrace” Business Plan and is funded by the European Investment Bank. In June 2014, construction works have commenced at NEA KRINI Station, which is included in the Thessaloniki Metro extension to Kalamaria, and constitutes the second Metro worksite after the TBM startup shaft.

Moreover, the infrastructure for the future extension of the Metro Line to the Airport is foreseen to be constructed together with a well-organized Bus Transfer Station in the area of Micra Station. A car parking facility is also planned to be constructed in the same Station.

This extension shall service more than 65,000 passengers, proportionally reducing the number of trips by private vehicles. It shall only take 15 minutes to cover the distance from Micra Station to the center of Thessaloniki. This project shall upgrade the municipality of Kalamaria in terms of transportation and environment, improving at the same time citizens’ every-day life.

PROGRESS OF WORKS

June 2018

• Kritis shaft: The permanent lining of the pumping station is completed.

• NOMARCHIA Station: The permanent lining at section 7 of the perimeter structures (ventilation shafts) and the backfilling and construction of the PUO networks in the area of the north access have been completed. Granite flooring, phase D1 of the traffic arrangement and paintwork in progress.

• Ceramic tile flooring and industrial floors are competed in the crossover

• KALAMARIA Station: Completed are the works for the construction of the foundation slab in the south ventilation shafts, the concrete cap beam and struts for the excavation of the east access, as well as wall plastering works on level -1. In progress the construction of the permanent lining of the south ventilation shafts and the installation of doors.

• ARETSOU Station: Wall have been constructed at level -1 and plastering has been completed on level -2. In progress is the construction of walls on level -2 and lining with fiber reinforced cement boards on level -2.

• PONTOU Shaft: Completion of the excavation and temporary retaining down to the bottom, as well as of the foundation slab. Permanent lining at the perimeter is in progress.

• MIKRA Station (& crossovers): Construction of walls on level -1 of the station. In progress the construction of the NE access staircase, of the south access parapet walls, of plastering works on level -1 and the station platform, the construction of industrial floors on level -1 of the station, the waterproofing of the roof slab and the paintwork in the 2nd crossover.

• TBM tunnels: Tunnel 2 boring works (TBM – ‘Elli”) are in progress at the 1st Micra crossover up to the “25 March” turnout, as well as the boring of tunnel 1 (TBM – ‘Frixos”) at the 1st Micra crossover up to Nomarchia Station.

Print Friendly, PDF & Email

May 2018

Kritis shaft: The excavation and temporary retaining of the pumping station have been completed.

• NOMARCHIA Station: Completed are the construction of the permanent lining of the north access, as well as the construction of industrial floors at level -2. The backfilling and construction of PUO networks in the area of the north access are in progress.

• KALAMARIA Station: Completed are the works for the excavation and temporary retaining of the SE ventilation shaft, for the construction of the west access and masonry works at level -2, as well as E/M installation works (sewerage of WC areas). The waterproofing of the SE ventilation shaft and the construction of the platform are in progress.

• ARETSOU Station: The construction of the west access and the E/M installations (sewerage of WC areas) have been completed. In progress is the construction of industrial floors and of walls / parapet walls at street level at the east access.

• NEA KRINI Station: The construction of industrial floors is in progress.

• MIKRA Station (& crossovers): Works for E/M installations – sewerage of sanitary areas have been completed. The construction of the south and NE accesses is in progress.

• TBM tunnels: Tunnel 1 boring works (TBM1 – ‘Frixos’) are in progress at ‘Nomarchia – 25 Martiou Crossover’ tunnel section.