Year: 2014

August 2014

NIKEA Station: The works for the construction of a foundation earthing system, soil improvement works and works for the acceptance of the main Station foundation invert have been completed. Excavation works and works for the removal of the muck (removal of the excavated material from the Station NATM tunnel access),…
Μάθε Περισσότερα

August 2014

New Railway Station: The works for the construction of a northern-west and northern-east manhole and the reinstatement of openings at level 1 of the crossover are in progress; AGHIA SOFIA Station: The archaeological excavation at the southern section of the Station is in progress; SINTRIVANI Station: The works for the…
Μάθε Περισσότερα

August 2014

Investigation trenches have been drilled at the locations where twin underground litter bins at Gr. Lambraki Street are to be placed; The works for the construction of Myrtidiotissas bridge have commenced, while the technical works in several locations of the TRAMWAY route are in progress (in the area where KARAISKAKI…
Μάθε Περισσότερα

THESSALONIKI METRO – Concert of Thessaloniki State Symphony Orchestra in THESSALONIKI METRO PANEPISTIMIO Station

On Friday August 29th 2014, ATTIKO METRO S.A. and Thessaloniki State Symphony Orchestra co-organised a concert in Thessaloniki Metro PANEPISTIMIO Station, which was given before a major number of spectators. The Station was inundated with Mozart sounds during a concert that created more than positive impressions, proving that Metro and…
Μάθε Περισσότερα

July 2014

NEW RAILWAY Station: The construction of the NW & NE shaft, as well as the restoration of openings (level 1) at the crossover, are in progress; DIMOKRATIAS Station: The construction of the southern part of the roof slab was completed; PANEPISTIMIO Station: The excavation of level 4 has commenced; PAPAFI…
Μάθε Περισσότερα

July 2014

AGHIA VARVARA Station: The works for the construction of the platform columns and floor slab are currently in progress; KOLYDALLOS Station: Completion of the works related to the drilling, embedding and tensioning of the pres-stressed anchors, as well as of the Station’s raft concreting works; NIKEA Station: In progress are…
Μάθε Περισσότερα

July 2014

Technical works are currently in progress at various locations along the tramway route. More specifically, the construction of the foundation piles for Myrtidiotissa Bridge at SEF terminal Stop has been completed, while other works are currently in progress. Moreover excavations in the area of Lambraki reversing point have been completed,…
Μάθε Περισσότερα

July 2014

The works for the construction of piles for peripheral retaining, as well as excavation works at NEA KRINI Station have commenced; The preparation, review and approval of the designs for the relocation and diversion of PUO networks, the traffic arrangements-diversions and the final designs of the stations are at an…
Μάθε Περισσότερα