AGHIA VARVARA Station: The works for the construction of supporting columns up to the platform level were completed, while the works for the construction of parapet walls and the platform floor are in progress; NIKEA Station: The works for the temporary drainage of the final excavation floor of the main…
Μάθε Περισσότερα

September 2014

NEW RAILWAY Station: The works for the restoration of openings (level 1) at the crossover were completed; DIMOKRATIAS Station: The works for the traffic phase modification were completed; AGHIA SOFIA Station: The archaeological excavation (Phase A’) at the southern part of the Station was completed; SINTRIVANI Station: The works for…
Μάθε Περισσότερα

September 2014

The survey – through investigation trenches – of the locations where dual underground litter bins are constructed is in progress at the sidewalks of Grigoriou Lambraki street (at the sidewalk opposite of and next to the tramway corridor); The urban planning works at the traffic island between Mikras Asias and…
Μάθε Περισσότερα

September 2014

NOMARCHIA Station: The works for the construction of shafts for the diversion of the sewage network have commenced; KALAMARIA Station: The works for the diversion of PUO networks have commenced; MIKRA Station: The excavation and retaining works at the TBMs access shaft are in progress; The preparation of designs is…