Year: 2015

November 2015

KORYDALLOS Station: The works for the waterproofing of the station are in progress. MANIATIKA Station: The excavation and temporary retaining works of phase A1 (eastern gallery) and phase A2 of the southern front of the station’s main tunnel are in progress. PIRAEUS Station: The preparation works for the construction of…
Μάθε Περισσότερα

November 2015

In progress are the relocations of the following PUO networks: EYDAP (water supply and sewage) networks – PPC & and EPA at the sidewalk adjacent to Grigoriou Lambraki street, Sewage – EPA & Fiber Optics at Vassileos Georgiou, EPA at Akti Possidonos, OTE & Fiber Optics at Ethn. Antistaseos street,…
Μάθε Περισσότερα

November 2015

NOMARCHIA Station: Works for the perimeter piles and piles cap beam have been completed, while the construction of struts made of reinforced concrete at level -1 are in progress. NOMARCHIA Crossover: Works for the construction of perimeter retaining piles and their cap beam have been completed. The works for the…
Μάθε Περισσότερα

October 2015

AGHIA VARVARA Station: The works for the removal of precast segments of the false tunnel are in progress; MANIATIKA Station: In progress are the excavation and temporary retaining works of phase A1 (south front – eastern gallery and north front – western gallery) of the station’s main tunnel. In progress…
Μάθε Περισσότερα

October 2015

In progress are the relocations of the following PUO networks: sewage and EPA at Vassileos Georgiou, EYDAP (water supply and sewage) networks at the sidewalk adjacent to Grigoriou Lambraki street, sewage and EPA networks at Omiridou Skylitsi street, OTE & fiber optics at Ethn. Antistaseos street & street lighting at…
Μάθε Περισσότερα

October 2015

NOMARCHIA Station: Works for the phase A excavation, the construction of struts at level -1 and the perimeter piles cap beam are in progress; NOMARCHIA Crossover: Works for the construction of perimeter retaining piles and their cap beam, as well as works for the diversion of PUO networks are in…
Μάθε Περισσότερα

ATHENS METRO – Important recognition of the work of ATTIKO METRO S.A. – The ATHENS METRO ranked among the top 10 in the world

ATTIKO METRO S.A. (AM) once again becomes the recipient of an important recognition of its work. This time, the acknowledgement comes of the USA. More specifically, Frommer’ s travel guide, ranked the Athens Metro among the top ten metro systems in the world, on account of the fact that numerous…
Μάθε Περισσότερα

September 2015

AGHIA VARVARA Station: The works for the construction of perimeter walls and columns up to the mechanical floor level, as well as the works for the construction of the mechanical floor slab are in progress; NIKEA Station: The construction of a part of the roof slab of the main Station,…
Μάθε Περισσότερα