Month: September 2016

August 2016

At Mikras Asias street, in progress are the works for the construction of the tramway corridor at Papandreou Bridge. At Grigoriou Lambraki street, the construction of the tramway corridor from the U-turn up to Venizelou Street, along with the urban planning of Lambraki and Evangelistrias stops are completed. The construction…
Μάθε Περισσότερα

August 2016

NOMARCHIA Station: The works for the construction of the foundation slab are in progress. KALAMARIA Station: The works for the temporary retaining of the metal struts up to the 4th level are in progress. ARETSOU Station: The installation of metal struts at the 2nd level has been completed. In progress…
Μάθε Περισσότερα

August 2016

NEW RAILWAY Station: The works for the construction of retaining piles in the shafts and the diversion of the combined-flow network are in progress. DIMOKRATIAS Station: the excavation works are completed, while in progress are the preparatory works for the subsequent traffic phase. AGHIA SOFIA Station: The works for the…
Μάθε Περισσότερα

August 2016

Komninou Shaft: The works for the worksite installations (building crane, settlement tank installation) are in progress. AGHIA VARVARA Station: The works for the construction of slabs at all levels are completed. At M. Alexandrou Shaft, completed is the worksite installation, while in progress are excavation and temporary retaining works. NIKEA…
Μάθε Περισσότερα