THESSALONIKI METRO: Tunnel Boring Machine: “Full steam ahead” for Kalamaria

The Tunnel Boring Machine “Elli” will reach ARETSOU Station (located at the junction of Tsigiridou and Aghiou Nikolaou Streets), the second station of the Metro extension to Kalamaria, tomorrow. Mr. Christos Spirtzis, Minister of Infrastructure and Transport, the Management of ATTIKO METRO S.A., representatives of the Contracting Company and persons…
Μάθε Περισσότερα

Athens Metro, a new era begins. Line 4: The Procedure for the Submission of the Envelopes for the Expression of Interest is completed

The procedure related to the submission of the envelopes for the expression of interest for participation in the Tender “LINE 4 – SECTION Α΄, ALSOS VEIKOU – GOUDI – STAGE A’ OF THE TENDER” was completed today on Thursday August 10th 2017, at 11.00. The schemes that participated in the…
Μάθε Περισσότερα

For the first time ATTIKO METRO S.A. expresses its intention to participate in the bidding process for undertaking projects abroad

Further to the visit of the Minister of Infrastructures and Transport, Christos Spirtzis and the Chairman of the ATTIKO METRO S.A. BoD, Professor Yannis A. Mylopoulos to Israel on July 24th and 25th 2017, on Thursday August 3rd 2017 – and for the first time – ATTIKO METRO S.A. expressed…
Μάθε Περισσότερα

April 2017

NOMARCHIA Station: The permanent lining at level -1 has been completed. Works for the construction of the slab at level -2 are in progress. • KALAMARIA Station: The construction of the permanent lining at level -3 has been completed. The construction of the slab at level -2 is in progress.…
Μάθε Περισσότερα

April 2017

• NEW RAILWAY Station: The archaeological excavation at the south shafts is complete. The excavation and the temporary retaining of the southern shaft are in progress. • DIMOKRATIAS Station: The construction of the temporary retaining at the southern access is in progress. • SINTRIVANI Station – EXPO: The construction of…