January 2017

• NOMARCHIA Station: The construction of the slab at level -2 has been completed, while in progress is the construction of the permanent lining from level -2 to level -1. • NOMARCHIA Crossover: In progress is the construction of the permanent lining from level -1 to the roof level. •…
Μάθε Περισσότερα

January 2017

• At Ethnarhou Makariou street, in progress is the construction of Karaiskaki stop and the staircase connecting this stop with the underground pedestrian walkway. • At Papandreou bridge and at Micras Asias Street, at the completion stage are the works for the construction of the tramway corridor (fitting of rails),…
Μάθε Περισσότερα

January 2017

• Along the double track tunnel, from the beginning of the extension up to TBM startup shaft, phases B’ and C’ excavation works of to Aghia Marina have been completed. In progress are the preparatory works for the demolition of the wall for connection with the tunnel. • AGHIA VARVARA…