Year: 2019

APRIL 2019

Α. Tramway The works for the construction of the tramway corridor (trackwork – rails – catenary) have been completed. The following works are in progress: The trial run of the Tramway system and the adjustment – checking of the systems and devices controlling the operation of the Tramway system (for…
Μάθε Περισσότερα

APRIL 2019

– TBM access shaft: The waterproofing of the ceiling slab +62.86 has been completed. – Komninou shaft: The works for the staircase balustrade have been completed, while architectural works (hatch construction) are in progress. AGHIA VARVARA Station: The works for the installation of granite slabs on the floor and walls…
Μάθε Περισσότερα

ΜΕΤΡΟ ΘΕΣΣΑΛΟΝΙΚΗΣ: ΑΝΑΚΟΙΝΩΣΗ ΠΡΟΣ ΤΑ ΜΜΕ

  ΑΝΑΚΟΙΝΩΣΗ ΠΡΟΣ ΤΑ ΜΜΕ Σας ενημερώνουμε ότι η άφιξη του πρώτου συρμού του Μετρό Θεσσαλονίκης θα πραγματοποιηθεί την Πέμπτη 16 Μαΐου 2019 και ώρα 10.00 π.μ., στο Αμαξοστάσιο Πυλαίας. Παρακαλούνται οι εκπρόσωποι των ΜΜΕ, οι οποίοι ενδιαφέρονται για δημοσιογραφική κάλυψη, να δηλώσουν συμμετοχή στα τηλέφωνα 2310-504714 και 2310 504754,…
Μάθε Περισσότερα

MARCH 2019

Α. Tramway The works for the construction of the tramway corridor (trackwork – rails – catenary) have been completed. The trial run of the Tramway system has commenced. Setting – checking of the systems controlling the operation of the Tramway system extension to Piraeus from the Central Control Room in…
Μάθε Περισσότερα

MARCH 2019

– TBM access shaft: The installation of an indoor steel plate has been completed. – Komninou shaft: Surface reinstatement is in progress. – Megalou Alexandrou shaft: Surface reinstatement is in progress. – Pissidias shaft: The final lining of Pissidias Shaft has been completed, screed placing at the treads of the…
Μάθε Περισσότερα