Day: February 15, 2019

JANUARY 2019

As regards the TRAMWAY NETWORK The works for the construction of the Tramway corridor have been completed (trackwork – rails – catenary) have been completed. The checking – arrangements – tests of the Tramway and catenary related installations are at the completion stage, while the trial running of the Tramway…
Μάθε Περισσότερα

JANUARY 2019

  TBM access shaft: the construction of slabs at level +47.46 has been completed, while the waterproofing of the roof slab at level +62.86 and the construction of parts of slabs at levels +56.11, +62.86 are in progress.   Komninou Shaft: Painting works have been completed, while the remaining architectural…
Μάθε Περισσότερα

January 2019

NOMARCHIA Station: Architectural works and works for the installation of E/M systems are in progress. KALAMARIA Station: The works for the construction of the east access, as well as the architectural and E/M installation works are in progress. ARETSOU Station: Architectural and E/M installation works are in progress. NEA KRINI…
Μάθε Περισσότερα