Month: November 2019

October 2019

Kritis Shaft: The works for the construction of the permanent lining are in progress. NOMARCHIA Station: The works for the construction of the terminations of shafts and their painting works have been completed. The works for the installation of granites at the platform and the construction of metal elements in the surrounding area are in […]
Read More

October 2019

VENIZELOU Station: The works for the dismantling of the metal bridge foundation base, a section of the southern diaphragm walls and the pile cap beans of the central piles are in progress. AGHIA SOFIA Station: The works for the construction of the foundation slab are in progress. PANEPISTIMIO Station: The works for the installation of […]
Read More

OCTOBER 2019

Α.            Tramway – Works for eliminating the risks from materials detached from the facades of the listed building at the junction of Omirou Skylitsi and Deligiorgi Streets have been completed. The tramway vehicles trial run has commenced a new. Β.            OTHER WORKS (reference to extended work fronts) Lambraki Bridge: Painting works have been completed. […]
Read More

OCTOBER 2019

DOUBLE TRACK ΝΑΤΜ START TUNNEL Works have been completed. KOMNINOU SHAFT The following works have been completed: Masonry works, plastering works, door installation, industrial floor, painting works, installation of grids at street level, staircase balustrades, hatch Reinstatement at street level AGHIA VARVARA STATION The following works are in progress: Reinstatement at street level – Square […]
Read More