Day: December 19, 2019

November 2019

NOMARCHIA Station: The works for the reinstatement of PUO networks and the configuration of the surrounding area are in progress. KALAMARIA Station: The following works are in progress: painting works at track level, backfilling of the surrounding area and reinstatement of PUO networks. ARETSOU Station: The works for the construction…
Μάθε Περισσότερα

NOVEMBER 2019

DOUBLE TRACK NATM START TUNNEL Works have been completed. KOMNINOU SHAFT The following works have been completed: Masonry, plastering, door installation, industrial floor, painting, grid installation at street level, staircase balustrades, hatch Street level reinstatement AGHIA VARVARA STATION The following works are in progress: Street – square level reinstatement Installation…
Μάθε Περισσότερα

The Minister of Transport and Infrastructures Kostas Ach. Karamanlis visiting the worksite of Pireaus station

Mr. Kostas Ach. Karamanlis, Minister of Transport and Infrastructures, Mr. Yiannis Kefalogiannis, Deputy Minister of Transport and Infrastructures, and Mr. Giorgos Karagiannis, Secretary General of Infrastructures visited the worksite of “Piraeus” Station on the Metro Line 3 extension from Aghia Marina to Dimotiko Theatro, on Thursday, December 19th, 2019. Statements…
Μάθε Περισσότερα