Day: May 5, 2020

March 2020

NEW RAILWAY Station: In progress are the works related to the installation of the sewage network at level -2, as well as the works for the construction of the Forestation platform. DIMOKRATIAS Station: The works for the installation of fire-rated air ducts of the tunnel ventilation system have been completed…
Μάθε Περισσότερα

March 2020

NOMARCHIA Station (station & crossover): The works for the installation of granites at the platform level have been completed. KALAMARIA Station: In progress are works for the reinstatement of the surrounding area, the paving of cement mortar for the sub-base of granites at the platform, as well as the works…
Μάθε Περισσότερα

March 2020

NEW RAILWAY Station: In progress are the works related to the installation of the sewage network at level -2, as well as the works for the construction of the Forestation platform. DIMOKRATIAS Station: The works for the installation of fire-rated air ducts of the tunnel ventilation system have been completed…
Μάθε Περισσότερα

February 2020

NOMARCHIA Station (station & crossover): In progress are the works for the installation of granites at the platform level, as well as the works related to sewage, earthing of electric trays and piping of the lighting network, power distribution and low voltage (weak currents) networks. KALAMARIA Station: In progress are…
Μάθε Περισσότερα

February 2020

NEW RAILWAY Station: In progress are the works related to the lift installation and the construction of filling concrete and sidewalk base. PAPAFI Station: The works for the installation of Platform Screen Doors (PSD) have been completed. In progress are earthing construction works. FLEMING Station: In progress are the works…
Μάθε Περισσότερα

January 2020

Kritis Shaft: The works for the construction of the permanent lining are in progress. NOMARCHIA Station (station & crossover): The works for the installation of galvanized balustrades and handrails are in progress. Moreover, in progress are the works for the installation of ventilation equipment, fire-rated air ducts, fire fighting networks…
Μάθε Περισσότερα