Day: May 15, 2020

April 2020

Kritis Shaft: The preliminary works for the construction of masonry walls are in progress. NOMARCHIA Station (station & crossover): The preliminary works for the reinstatement of the surrounding area and the works for the installation of a fire detection network are in progress. KALAMARIA Station: The works for the installation…
Μάθε Περισσότερα

April 2020

NEW RAILWAY STATION: The works for the construction of the filling concrete in the area of the forestation are in progress. DIMOKRATIAS Station: The works for the installation of a sewage network are in progress. VENIZELOU Station: The works for the removal of struts and monorail installation are in progress.…
Μάθε Περισσότερα