Day: July 22, 2020

June 2020

Kritis Shaft: The works for the construction of masonry walls and plastering works have been completed, while the works for door installation are in progress. NOMARCHIA Station: In progress are the works for the installation of glass doors at platform level and of windows in rooms 2.2 & 2.3, as…
Μάθε Περισσότερα

June 2020

NEW RAILWAY STATION: The works for the transport and distribution of rail-tracks are in progress. DIMOKRATIAS Station: The works for the transport and distribution of rail-tracks are in progress. VENIZELOU Station: The works for cutting the walls to encase the temporary backfill, as well as the preliminary works for the…
Μάθε Περισσότερα