Month: November 2020

Πρόοδος έργου Καλαμαριάς - Οκτώβριος 2020

October 2020

  KALAMARIA Station: Landing paving works at the staircase of the eastern entrance and works for the installation of scaffoldings for the installation of glass panels at the sheds of the eastern and western entrances are in progress. In progress are also works for the installation of earthing and cabling…
Μάθε Περισσότερα
Πρόοδος Βασικού Έργου Θεσσαλονίκης - Οκτώβριος 2020

October 2020

  VENIZELOU Station: Diaphragm walls construction works at the southern access have been completed. In progress are equipment and related facilities removal works, as well as works for the construction of temporary retaining piles at the southern access. AGHIA SOFIA Station:  Surface reinstatement works at the south section of the…
Μάθε Περισσότερα
Koridallos

OCTOBER 2020

  TZAVELA SHAFT The following works have been completed: Permanent lining of the bottom of the shaft Permanent lining of the connecting tunnel Removal of temporary steel frames for the support of the TBM tunnel Permanent lining of the perimeter wall of the shaft Permanent lining of interior parapet wall…
Μάθε Περισσότερα