KALAMARIA_12_20_1

December 2020

  Kritis Shaft: Reinstatement related works at street level, painting works and works related to the completion of door installation are in progress. KALAMARIA Station: In progress are reinstatement related works at street level, as well as works for the installation of glass panels of the sheds at the east…
Μάθε Περισσότερα
THESSALONIKI_12_20

December 2020

  NEW RAILWAY STATION: Works related to the construction of masonry walls and plastering related works have been executed. VENIZELOU Station: The works for the removal of the equipment and installations at the south access have been completed. AGHIA SOFIA Station: Works for the construction of parapet walls’ terminations at…
Μάθε Περισσότερα