TZAVELA SHAFT  The following works have been completed: Completion of the permanent lining of the shaft and of the connecting tunnel. MANIATIKA STATION STATION’s OPEN CUT The following works have been completed: Completion of the permanent lining of the shaft. The following works are in progress: Waterproofing of the roof…
Μάθε Περισσότερα

March 2021

  NOMARCHIA Station (Station and Crossover): Works for the installation of manhole covers, reinstatement related works at street level and works for the installation of HVAC system equipment are in progress. KALAMARIA Station: In progress are works for the installation of a metal structure to support the glass panels of…
Μάθε Περισσότερα

March 2021

    New Railway Station: Works for the installation of cable trays at the signaling and telecommunications technical rooms have been completed. Works for the installation of equipment of the fire fighting system in tunnels are in progress. DIMOKRATIAS STATION: Works related to the installation of the air ducts network…
Μάθε Περισσότερα

FEBRUARY 2021

TZAVELA SHAFT The following works have been completed: Completion of the permanent lining of the shaft and of the connecting tunnel. The following works are in progress: Masonry walls. MANIATIKA STATION STATION’s OPEN CUT The following works have been completed: Completion of the permanent lining of the shaft. The following…
Μάθε Περισσότερα