Day: April 12, 2021

MARCH 2021

TZAVELA SHAFT  The following works have been completed: Completion of the permanent lining of the shaft and of the connecting tunnel. MANIATIKA STATION STATION’s OPEN CUT The following works have been completed: Completion of the permanent lining of the shaft. The following works are in progress: Waterproofing of the roof…