Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

Month: June 2021

In the presence of Prime Minister Kyriakos Mitsotakis, the contract for the initiation of works for the construction of Athens Metro Line 4 was signed by ATTIKO METRO S.A. and “AVAX S.A. – GHELLA SpA – ALSTOM Transport S.A” Association

On June 22nd, 2021 the contract for the initiation of the works for the construction of Athens Metro Line 4 was signed by ATTIKO METRO S.A. and “AVAX S.A. – GHELLA SpA – ALSTOM Transport S.A” Association at Alsos Veikou Theatre, in the presence of Prime Minister Kyriakos Mitsotakis and…
Μάθε Περισσότερα

MAY 2021

TZAVELLA SHAFT The following works have been completed: Completion of the permanent lining of the shaft and of the connecting tunnel. Construction of sound absorbing plaster. MANIATIKA STATION STATION’s OPEN CUT       The following works have been completed: Completion of the permanent lining of the shaft. The following works are in…
Μάθε Περισσότερα

May 2021

NOMARCHIA Station (Station and Crossover): In progress are cladding works using fibre-cement boards at the central staircase, as well as works for the installation of the fire fighting network and HVAC system related networks. KALAMARIA Station: In progress are traffic arrangement works, works for the installation of metal frames and glass panels…
Μάθε Περισσότερα

May 2021

New Railway Station: In progress are vertical marble cladding works at level -1, works for the installation of fire-rated air ducts at platform level, as well as works for the configuration of the surrounding area, at the north part of the station. AGHIA SOFIA Station: In progress are masonry works at mezzanine…
Μάθε Περισσότερα
WCAG