Month: August 2021

July 2021

NOMARCHIA Station (Station & Crossover): Street-level reinstatement works, works for the installation of stainless steel balustrades and handrails at the entrance staircase and works for the installation of lighting fixtures are in progress. At the crossover, concreting works of the roof slab for closing of the opening and waterproofing works are in progress. KALAMARIA Station: Preliminary works for the implementation […]
Read More

July 2021

NEW RAILWAY STATION: In progress are works for the installation of cable trays at the Forestation tunnel, as well as works for the configuration of the surrounding area at the northern section of the station. DIMOKRATIAS Station: Completed are works for the closing of the temporary opening of the roof slab, as well as for the implementation […]
Read More

JULY 2021

TZAVELA Shaft  The following works have been completed: Completion of the permanent lining of the shaft and of the connecting tunnel. Construction of sound absorbing plaster. Traffic Arrangement – Phase B’ The following works are in progress: Reinstatement works at Tzavela and Lakonias Streets. MANIATIKA STATION STATION’s OPEN CUT       The following works have been completed: […]
Read More