SEPTEMBER 2018

  • Kritis shaft: The works for the construction of the perimeter permanent lining continue, while the works for the construction of connecting tunnels are in progress.
  • NOMARCHIA Station: The works for the construction of platforms are at an advanced stage, while the works for the construction of the lining of indoor walls are in progress.
  • KALAMARIA Station: The works for the construction of cladding of indoor walls, as well as the installation of escalators, are in progress.
  • ARETSOU Station: The works for the installation of doors at levels -1 and -2 have been completed, while painting works and works for the installation of ceramic tiles are in progress. The installation of escalators in the station has commenced.
  • NEA KRINI Station: The installation of cladding using ceramic tiles in WCs, as well as the installation of metal doors, have been completed, while painting works are in progress.
  • MIKRA Station (& crossovers): The backfilling of the roof slab at the Station, as well as at the 2nd crossover, is in progress. The works for the construction of masonry walls at the station are also in progress.
  • TBM tunnels: The disassembly of the 1st TBM has been completed, while the disassembly of the 2nd TBM is in progress. In progress are also the works for the removal of the TBM worksite facilities in the area of Micra 1st