OCTOBER 2018

    • Kritis shaft: The works for the construction of the connecting tunnels are in progress.
  • NOMARCHIA Station: The painting works are completed.
  • KALAMARIA Station: The works for the permanent lining of the eastern access of the Station are in progress.
  • ARETSOU Station: The works for the concreting and waterproofing of the temporary opening of the roof slab, as well as the installation of ceramic tiles at levels -1 and -2 have been completed.
  • NEA KRINI Station: The installation of indoor escalators has been completed, while painting works are at an advanced stage.
  • MIKRA Station: The works for the installation of the indoor staircases have been completed, while the works for the construction of level -1 slab at the 1st crossover are in progress.
    • Terminal Shaft: The paining works and the works for industrial flooring have been completed.  
    • TBM tunnels: The disassembly of the 1st TBM has been completed, while the disassembly of the 2nd TBM is in progress. In progress are also the works for the removal of the TBM worksite facilities in the area of Micra 1st