DECEMBER 2018

  • NOMARCHIA Station: Floor cladding works using granite slabs are in progress, while E/M installation works are at an initial stage.
  • KALAMARIA Station: Painting works are at an initial stage, while works for the construction of the platform and the construction of the north ventilation shaft have commenced.
  • ARETSOU Station: Floor lining works using granite slabs are at an initial stage, while painting works and platform construction works are at a satisfactory level.
  • NEA KRINI Station: Works for the construction of indoor walls lining and the construction of E/M installations advance at a satisfactory rate.
  • MIKRA Station (Station & Crossovers): Slab construction works at level -1, at the 1st crossover, have been completed, while the works for the construction of the perimeter permanent lining, at the 1st crossover, are in progress. Moreover, the works for the excavation and temporary retaining of the NW access and the south ventilation shaft are at an initial stage.
  • Forestation: The works for the construction of industrial floors and the installation of doors are at an initial stage. Moreover, works for the construction of trackwork are in progress.
  • TBM tunnels: The construction of pumping stations related continue.