NOVEMBER 2019

DOUBLE TRACK NATM START TUNNEL

Works have been completed.

KOMNINOU SHAFT

The following works have been completed:

  • Masonry, plastering, door installation, industrial floor, painting, grid installation at street level, staircase balustrades, hatch
  • Street level reinstatement

AGHIA VARVARA STATION

The following works are in progress:

  • Street – square level reinstatement
  • Installation of handrails
  • Other architectural finishes

MEGALOU ALEXANDROU SHAFT

Works have been completed.

The following works are still pending:

  • Planting (street level)

TAXIARCHON SHAFT

The following works are in progress:

  • Installation of doors
  • Installation of ceramic tiles
  • Installation of metal structures

KORYDALLOS STATION

The following works are in progress:

  • Installation of doors
  • Installation of granites or marbles
  • Wall and Columns cladding
  • Installation of ventilation grids
  • Painting

NIKEA STATION

MAIN STATION

The following works are in progress:

  • Final reinstatement (slab paving) at level -0 of the street
  • Roof lining at various levels of the Station
  • Wall cladding using granite slabs and metal cladding at various levels of the Station.

 MANIATIKA STATION

OPEN CUT OF THE STATION

The following works are in progress:

  • Permanent lining of E/M slab (level -3)
  • Permanent lining of staircase S4

DIMOTIKO THEATRO STATION

MAIN STATION – AGHIOU KONSTANTINOU SQUARE

The following works are still pending:

  • Door installation at the E/M floor
  • Waterproofing at street level

 The following works are in progress:

  • Painting at the E/M floor, at the ticketing and platform levels
  • Plastering at platform level.

 

 

 