November 2019

VENIZELOU Station: The works for the installation of the roof slab in the southern part of the station are in progress.

AGHIA SOFIA Station: The works for the construction of the foundation were completed. The works for the construction of the platform, of the southern ventilation shafts and the water proofing related activities at the southern entrance are in progress.

DEPOT:

Building Complex ΙΙ: The works for the installation of handrails and the windbreak as well as the manufacturing of concrete suitable for the configuration of sloping are in progress.

In progress are the works for the installation of E/M installations in the following stations: NEW RAILWAY, SINTRIVANI/EXPO, PANEPISTIMIO, PAPAFI, EFKLIDIS, ANALIPSI (Station and Crossover), 25TH MARTIOU (Station and Crossover) and NEA ELVETIA.

 