Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

DECEMBER 2019

DOUBLE TRACK NATM START TUNNEL

Works have been completed.

KOMNINOU SHAFT

The following works have been completed:

  • Masonry, plastering, door installation, industrial floor, painting, grid installation at street level, staircase balustrades, hatch
  • Street level reinstatement

AGHIA VARVARA STATION

The following works are in progress:

  • Installation of lifts in the station
  • Wall and columns cladding (metal, glass etc.)
  • Installation of handrails
  • Other architectural finishes
  • Installation of station and other signs
  • Installation of a fountain
  • Planting and irrigation system
  • Installation of false ceilings at the ticketing level.

MEGALOU ALEXANDROU SHAFT

Works have been completed.

The following works are still pending:

  • Planting (street level)

TAXIARCHON SHAFT

The following works are in progress:

  • Painting works
  • Filling works and industrial floors
  • Installation of doors
  • Installation of ceramic tiles
  • Installation of metal structures

KORYDALLOS STATION

The following works are in progress:

  • Installation of doors
  • Installation of granites or marbles
  • Wall and Columns cladding
  • Installation of false ceilings
  • Installation of lift at street level
  • Installation of handrails
  • Installation of balustrades

PISSIDIAS SHAFT

The following works are in progress:

  • Handrails – balustrades at the emergency staircase
  • Final reinstatement at street level (removal – dismantling).

NIKEA STATION

MAIN STATION

The following works are in progress:

  • Roof cladding using horizontal false ceiling panels at several levels of the Station
  • Wall cladding using metal panels at level -3 of the platforms
  • Final reinstatement of the surrounding area at street level (slab paving – minor structures’ concrete)
  • Installation of metal shed at the central entrance of the Station
  • Installation of metal structure to support the glass panels of the PSN lifts
  • Preliminary works for the installation of fire rated glass panels at the public staircases, at level -3 of the platforms
  • Preliminary works for the installation of aluminum glass panels in public areas, at level -1 of the E/M floor.

MANIATIKA STATION

OPEN CUT OF THE STATION

The following works have been completed:

  • Permanent lining of foundation (level -4)
  • Permanent lining of E/M slab (level -3)
  • Permanent lining of staircase S4

DIMOTIKO THEATRO STATION

MAIN STATION – AGHIOU KONSTANTINOU SQUARE

The following works are still pending:

  • Door installation at the E/M floor
  • Waterproofing at street level

The following works are in progress:

  • Concreting of the east shaft termination
  • Filing concrete underneath the platforms.
Print Friendly, PDF & Email
WCAG