Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

FEBRUARY 2020

 

AGHIA VARVARA STATION

The following works are in progress:

  • Installation of lifts in the station
  • Wall and columns cladding (metal, glass etc.)
  • Installation of balustrades
  • Installation of handrails
  • Other architectural finishes
  • Installation of a fountain
  • Planting and irrigation system
  • Installation of false ceilings at the ticketing level
  • Square reinstatement (Granites, Passageways, Marbles).

MEGALOU ALEXANDROU SHAFT

The following works are still pending:

  • Planting (street level).

TAXIARCHON SHAFT

The following works are in progress:

  • Painting works
  • Configuration at street level.

KORYDALLOS STATION

The following works are in progress:

  • Wall and Columns cladding
  • Installation of false ceilings
  • Installation of balustrades
  • Installation of roller shutters
  • Installation of irrigation system at street level
  • Installation of signage
  • Installation of Station entrances’ sheds
  • Installation of lift at street level
  • Configuration at street level (Eleftherias Square)

PISSIDIAS SHAFT

The following works are in progress:

  • Final reinstatement at street level

NIKEA STATION

MAIN STATION

The following works are in progress:

  • Final reinstatement of the surrounding area
  • Painting of parapet walls of the superstructure
  • False ceilings
  • Floor paving using granite slabs
  • Wall cladding using metal panels
  • Station signage.

PIRAEUS STATION 

STATION

The following works have been completed:

  • Installation and prestressing of struts for temporary retaining at all levels
  • Installation of waterproofing and concreting of the foundation (bay 4).

DIMOTIKO THEATRO STATION

MAIN STATION – AGHIOU KONSTANTINOU SQUARE

The following works are still pending:

  • Door installation at the E/M floor.

The following works are in progress:

  • Masonry walls at ticketing level
  • Waterproofing at street level
  • Backfilling – compaction related works
  • Cleaning works

UNDERGROUND PART OF THE STATION

The following works have been completed:

  • Concreting of the permanent lining, parapet walls and platform slab.

STAIRCASE GALLERIES

The following works have been completed:

  • Concreting of the permanent lining and works related to secondary concreting.

 

 

Print Friendly, PDF & Email
WCAG