Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

NEW RAILWAY Station: In progress are the works related to the automatic extinguishing system using gas and to the tunnel ventilation equipment.

DIMOKRATIAS Station (Station and Crossover): In progress are the works related to the network for fire fighting and installation of fire-rated air ducts of the tunnel ventilation and air supply system.

AGHIA SOFIA Station: In progress are the works for the construction of the permanent lining of the northern and southern accesses, the connections of the station with the tunnel, as well as the works for the repair of diaphragm walls.

SINTRIVANI/EXPO Station: The works for the installation and connections of the fire detection equipment are in progress.

PANEPISTIMIO Station: The works for the installation of Platform Screen Doors (PSD) have been completed, while in progress are the works for the construction of equipment earthing and the installation of air ducts of the ventilation/air conditioning system.

PAPAFI Station: In progress are the works for the installation of Platform Screen Doors (PSD), the installation of the lighting system, as well as the works for the installation of the ventilation/air conditioning equipment.

EFKLIDIS Station: In progress are the works for the installation of the lighting system and for the installation of the tunnel ventilation equipment.

FLEMING Station: The works for the completion of the air ducts network are in progress.

ANALIPSI Station (Station and Crossover): The works for the construction of trackwork are in progress.

25TH MARTIOU Station: In progress are the works for the installation of air ducts of the ventilation-A/C system, the works for the construction of equipment earthing, as well as the works for the construction of pedestrian walkways in the crossover area.

DEPOT:

Building Complex Ι: In progress are the works for the construction of masonry of the vehicles’ washing plant, of gypsum boards, the outdoor staircase in the test track area, as well as the works for the installation of cables and the signalling equipment.

Building Complex ΙΙ: In progress are the works for the construction of gypsum boards and painting works, works for the lift installation, the ventilation-A/C equipment, in-floor cable ducts and cables of the fire detection system.

TBM tunnels: The construction of trackwork at a specific section of the Project tunnels is in progress.

Print Friendly, PDF & Email
WCAG