January 2020

Kritis Shaft: The works for the construction of the permanent lining are in progress.

NOMARCHIA Station (station & crossover): The works for the installation of galvanized balustrades and handrails are in progress. Moreover, in progress are the works for the installation of ventilation equipment, fire-rated air ducts, fire fighting networks and electric trays.

KALAMARIA Station: In progress are backfilling works, works for the reinstatement of the surrounding area, for the relocation of PUO networks, as well as works for the installation of electric trays and fire fighting networks.

ARETSOU Station: In progress are reinstatement works at street level, works for the installation of galvanized balustrades and handrails, for cladding with fiber-cement boards, as well as works for the installation of electric trays.

MIKRA Station (Station & Crossovers): In progress are backfilling works, works for the installation of fibre-cement boards and works for the installation of tunnel ventilation systems.

TBM tunnels: The works for the construction of trackwork at a tunnel section are in progress.