NEW RAILWAY Station: In progress are the works related to the installation of the sewage network at level -2, as well as the works for the construction of the Forestation platform.

DIMOKRATIAS Station: The works for the installation of fire-rated air ducts of the tunnel ventilation system have been completed and in progress are the works for the installation of the automatic fire extinguishing system.

VENIZELOU Station: In progress are the preparatory works for the removal of struts.

AGHIAS SOFIAS Station: The construction of the station connections with the tunnels has been completed. In progress are the works for the construction of walls and of the top of the SW shaft, as well as works related to the water tightness of diaphragm walls.

SINTRIVANI Station: In progress are installation works and works related to connections of the tunnel ventilation equipment.

PANEPISTIMIO Station: In progress are the works related to the electric connections of escalators.

PAPAFI Station: In progress are the installation of tunnel ventilation equipment and the installation of lighting cables at track 1 tunnel.

ANALIPSI Station (Station and Crossover): In progress are the works for the installation of lighting cable ducts at the platform.

25TH MARTIOU Station (Station and Crossover): Lift installation works are in progress.

DEPOT:

 Building Complex Ι: In progress are works for the construction of tiles at the washing plant, the installation of roller shutters, at levels +52 and +58, as well as the works for the installation of signalling and A/C network cables.

 Building Complex ΙΙ: In progress are the works for the construction of gypsum boards, the installation of the fire fighting network, the A/C network, the installation of cable trays, of the lightning protection, as well as the installation of lifts.

TBM tunnels: The construction of trackwork at a specific section of the Project tunnels is in progress.