Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

NEW RAILWAY STATION: The works for the transport and distribution of rail-tracks are in progress.

DIMOKRATIAS Station: The works for the transport and distribution of rail-tracks are in progress.

VENIZELOU Station: The works for cutting the walls to encase the temporary backfill, as well as the preliminary works for the construction of the rails of the southern access diaphragm walls are in progress.

AGHIA SOFIA Station: The construction of the inner staircase, as well as the works for the construction of masonry walls at mezzanine level and level -1, along with the works for the installation of the sewage network at levels -2 and -3 are in progress.

PANEPISTIMIO Station: The works for the construction of track’s floating slab are in progress.

PAPAFI Station: The works for the installation of cables for tunnel lighting are in progress.

EFKLIDIS Station: The works for the installation of a traction power equipment bases in the technical room, as well as the works for the installation of BACS cables are in progress.

FLEMING Station: The works for the pumping station waterproofing are in progress.

ANALIPSI (Station and Crossover): The works for the installation of turnouts are in progress.

25 MARTIOU (Station and Crossover): The works for the installation of Access and Intrusion Detection system equipment, along with the works for the construction of trackwork (track bed concreting) are in progress.

VOULGARI Station: The preparatory works for track bed concreting are in progress.

NEA ELVETIA Station: The supporting beam related works for PSDs, as well as the works for the radio system installation control are in progress.

DEPOT:

  • Building Complex Ι: The works for laying tiles in the washing plant area, for the installation of furniture in the ECR, as well as for the installation of the fire fighting network at +58.00, of cable trays at +52.00 and +69.00, along with the works for the installation of a lighting system at +52.00 are in progress.
  • Building Complex ΙΙ: The installation of the fire fighting network at +70.40, the installation of the air-conditioning and cable trays networks at +58.00, as well as the works for the installation of the radio system equipment at +53.00 are in progress.  In addition, the works for the installation of the signalling equipment (track circuits) are in progress.

Trackwork: Track bed 1 concreting works along with the installation of precast cable ducts of the C/C tunnel; from Nea Elvetia Station to the Depot are completed; the track 2 floating slab between “Sintrivani Crossover – Panesipstimio Station” and Analipseos Crossover floating slab construction works are in progress. The track bed concreting works between Analipsi and Voulgari Stations, along with the works for the transport and distribution of rail-tracks in the section of the tunnels between NEW RAILWAY station and AGHIA SOFIA Station are in progress.

Print Friendly, PDF & Email
WCAG