AUGUST 2020

Πρόοδος Πειραιά - ΑΥΓΟΥΣΤΟΣ 2020
[responsivevoice_button voice=”UK English Female” buttontext=”Listen to post”]

 

MANIATIKA STATION

STATION’s C/C

The following works have been completed:

  • Waterproofing of perimeter parapet walls
  • Permanent lining of the foundation (level -4)
  • Permanent lining of E/M slab (level -3)
  • Permanent lining of the ticketing area slab (level -2)
  • Permanent lining of staircace S4
  • Permanent lining of E/M slab (level -1)
  • Permanent lining of perimeter walls and columns
  • Permanent lining of the roof slab and staircase S3
  • Construction of perimeter walls of the station’s main entrance (at street level) and of the inclined part of the main entrance (shed).

The following works are in progress:

  • Waterproofing of the roof slab
  • Construction of masonry walls and execution of plastering works at levels -4,-3 and -1.

MAIN TUNNEL OF THE STATION (ΝΑΤΜ)

The following works have been completed:

  • Permanent lining of the station’s main tunnel
  • Permanent lining of the deepening area
  • Permanent lining of the northern and southern headwall
  • Construction of parapet walls and platform slabs
  • Secondary grouting of the vault of the main station tunnel
  • Filling of platform ducts with non-reinforced concrete.

PIRAEUS STATION 

The following works have been completed:

  • Concreting of the foundation slab and placing of non-reinforced concrete over the foundation.

The following works are in progress:

  • Installation of waterproofing of the station’s parapet walls and in areas of the north and south front
  • Concreting of the station’s perimeter walls and of the walls underneath the platforms
  • Concreting of platform slabs
  • Re-installation of the 5th row of struts at a new location and removal of the 3rd and 4th rows of struts
  • Concreting of slab at level -2 (section 4).

ROLOI SHAFT

The following works have been completed:

  • Construction of foundation and permanent lining of perimeter walls (still pending is the termination at street level).

The following works are in progress:

  • Construction of intermediate parapet wall (up to +1.50) and staircase (down to -1.70).

NATM ACCESS TUNNEL

The following works have been completed:  

  • Concreting of the permanent lining.

DIMOTIKO THEATRO STATION

MAIN STATION – AGHIOU KONSTANTINOU SQUARE

The following works have been completed:

  • Sealing of the temporary pumping station.

The following works are in progress:

  • Cleaning works
  • Preliminary works for roof painting at platform level

UNDERGROUND PART OF THE STATION

The following works have been completed:

  • Concreting of the permanent lining, parapet walls and platform slab.

The following works are in progress:

  • Preliminary works for painting the vault.

STAIRCASE GALLERIES

The following works have been completed:

  • Concreting of the permanent lining and works related to secondary concreting.

KORAI SQUARE ENTRANCE AND ACCESS GALLERY

The following works have been completed:

  • Concreting of the permanent lining, secondary concrete and waterproofing.

The following works are in progress:

  • Backfilling – compaction related works in C/C.

BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY

 The following works have been completed:

  • Waterproofing and concreting of the permanent lining (still pending is the waterproofing detail at the terminating point, at street level)
  • Secondary concrete at the staircases.

The following works are put on hold:

  • Secondary concrete at the access gallery.

DELIGIANNI SHAFT

The following works have been completed:

  • Excavation and temporary retaining up to the final level
  • Waterproofing, construction of foundation slab and perimeter parapet walls down to -3.0.

PANEPISTIMIO SHAFT & VENTILATION TUNNEL

The following works have been completed:

  • Excavation – temporary retaining
  • Concreting of the foundation of the shaft’s permanent lining
  • Concreting of floor and parapet walls of the permanent lining of the connecting tunnel.

The following works are in progress:

  • Concreting of the vault of the connecting tunnel.

 

 

 

 