OCTOBER 2020

Koridallos
iso

 

TZAVELA SHAFT

The following works have been completed:

  • Permanent lining of the bottom of the shaft
  • Permanent lining of the connecting tunnel
  • Removal of temporary steel frames for the support of the TBM tunnel
  • Permanent lining of the perimeter wall of the shaft
  • Permanent lining of interior parapet wall and staircase
  • Permanent lining of the slab at level +8.57

MANIATIKA STATION

STATION’s C/C

The following works have been completed:

  • Waterproofing of perimeter parapet walls
  • Permanent lining of the foundation (level -4)
  • Permanent lining of E/M slab (level -3)
  • Permanent lining of the ticketing area slab (level -2)
  • Permanent lining of staircace S4
  • Permanent lining of E/M slab (level -1)
  • Permanent lining of perimeter parapet walls and columns
  • Permanent lining of the roof slab and staircase S3
  • Construction of perimeter parapet walls of the station’s main entrance (at street level) and of the inclined part of the main entrance (shed).

The following works are in progress:

  • Waterproofing of the roof slab
  • Construction of masonry walls and execution of plastering works at levels -4,

-3, -2 and -1.

MAIN TUNNEL OF THE STATION (ΝΑΤΜ)

The following works have been completed:

  • Permanent lining of the station’s main tunnel
  • Permanent lining of the deepening area
  • Permanent lining of the northern and southern headwall
  • Construction of parapet walls and platform slabs
  • Secondary grouting of the vault of the main station tunnel
  • Filling of platform ducts with non-reinforced concrete.

PIRAEUS STATION 

The following works have been completed:

  • Waterproofing works under the foundation
  • Concreting of the foundation slab and placing of non-reinforced concrete over the foundation.
  • Concreting of platforms and vertical elements underneath the platforms.

The following works are in progress:

  • Installation of waterproofing of the station’s parapet walls
  • Concreting of the station’s perimeter parapet walls and of the parapet walls underneath the platforms
  • Concreting of E/M slab
  • Removal of struts and sleepers of the 3rd and 4th rows
  • Concreting of inner parapet walls and columns
  • Works for the concreting of the passenger circulation slab.

ROLOI SHAFT

The following works have been completed:

  • Construction of foundation and permanent lining of perimeter parapet walls.

NATM ACCESS TUNNEL

The following works have been completed:

  • Concreting of the permanent lining.

DIMOTIKO THEATRO STATION

MAIN STATION – AGHIOU KONSTANTINOU SQUARE

The following works have been completed:

  • Sealing of the temporary pumping station.

The following works are put on hold:

  • Installation of doors at E/M level.

The following works are in progress:

  • Cleaning works
  • Plastering works at the E/M, concourse and platform levels
  • Roof and headwall painting works at platform level
  • Conservation of the archaeological finds of the Project.

UNDERGROUND PART OF THE STATION

The following works have been completed:

  • Concreting of the permanent lining, parapet walls and platform slab.

The following works are in progress:

  • Painting works at the vault.

 STAIRCASE GALLERIES

The following works have been completed:

  • Concreting of the permanent lining and works related to secondary concreting.

KORAI SQUARE ENTRANCE AND ACCESS GALLERY

 The following works have been completed:

  • Concreting of the permanent lining, secondary concrete and waterproofing.

The following works are in progress:

  • Dismantling of the pile cap beam.
  • Backfilling – compaction related works.

BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY

 The following works have been completed:

  • Waterproofing and concreting of the permanent lining (still pending is the waterproofing detail at the terminating point, at street level)
  • Secondary concrete at the staircases.

The following works are put on hold:

  • Secondary concrete at the access gallery.

 The following works are in progress:

  • Waterproofing works at the roof
  • Backfilling – compaction related works.

DELIGIANNI SHAFT

 The following works have been completed:

  • Excavation and temporary retaining up to the final level
  • Waterproofing, construction of foundation slab and perimeter parapet walls down to -3.0.

 PANEPISTIMIO SHAFT & VENTILATION TUNNEL

 The following works have been completed:

  • Excavation – temporary retaining
  • Concreting of the foundation of the shaft’s permanent lining
  • Concreting of the permanent lining of the connecting tunnel.

The following works are in progress:

  • Waterproofing works and installation of reinforcement for the permanent lining of perimeter parapet walls.