Πρόοδος έργου Καλαμαριάς - Οκτώβριος 2020

 

KALAMARIA Station: Landing paving works at the staircase of the eastern entrance and works for the installation of scaffoldings for the installation of glass panels at the sheds of the eastern and western entrances are in progress. In progress are also works for the installation of earthing and cabling for lighting networks.

ARETSOU Station: Infrastructure construction works for irrigation and fire-fighting networks, painting works in public areas and painting works of galvanized balustrades in technical rooms are in progress.

Pontou Shaft: Works for the construction of industrial flooring have been completed.

NEA KRINI Station: In progress are works for the installation of sound panels.

Terminal Shaft: In progress are works for the installation of galvanized balustrades

TRACKWORK

Moreover, concreting works on tracks 1 & 2 from K.P. 0+0.91 up to Nomarchia Crossover and the installation of precast ducts on the sidewalks of track 1 from K.P. 2+800 up to the 2nd Crossover have been completed.